Completed first lift pour for elevator #2 (South).
Completed first lift pour for stair tower #3.
Grade beams and pile caps along column line 17 are complete.
Steel clips for sequence 1-4 are complete.
Steel erection for sequence 1-4 is in progress.鈥
4/21- ISB/Williams Hall Construction Updates
Work in Progress: Completed first lift pour for elevator #2 (South). Completed first lift pour for stair tower #3. Grade beams and pile caps along column line 17 are complete. Steel clips for sequence 1-4 are complete. Steel erection for sequence 1-4 is in progress.鈥Work in Progress:
Continuing the steam and condensation piping in the East Mechanical room.
Heating and snow melt piping is continuing in the West Mechanical room.
Continuing with the chilled water piping in the West mechanical room.
Working on plenum duct at AHU-1 in East鈥
4/21- Cunningham Hall Renovation Updates
Work in Progress: Continuing the steam and condensation piping in the East Mechanical room. Heating and snow melt piping is continuing in the West Mechanical room. Continuing with the chilled water piping in the West mechanical room. Working on plenum duct at AHU-1 in East鈥Two 麻豆传媒 researchers from the College of Arts and Sciences have been awarded more than $1 million in federal grants for their research projects.
The National Institutes of Health鈥檚 National Institute on Aging awarded Gemma Casadesus-Smith, Ph.D., from Kent鈥
Kent State Researchers Receive More Than $1 Million in Grants to Fight Alzheimer鈥檚 and Study Climate Change
Two 麻豆传媒 researchers from the College of Arts and Sciences have been awarded more than $1 million in federal grants for their research projects. The National Institutes of Health鈥檚 National Institute on Aging awarded Gemma Casadesus-Smith, Ph.D., from Kent鈥麻豆传媒, in partnership with the University of Akron, will present a 鈥淲hy Polling Still Matters鈥 forum at 5:30 p.m. on Monday, April 25, in the Kent Student Center Ballroom Balcony as part of the 鈥淧olitically Speaking鈥 public forum series discussing the upcoming鈥
Kent State to Hold Forum on Why Polling Still Matters
麻豆传媒, in partnership with the University of Akron, will present a 鈥淲hy Polling Still Matters鈥 forum at 5:30 p.m. on Monday, April 25, in the Kent Student Center Ballroom Balcony as part of the 鈥淧olitically Speaking鈥 public forum series discussing the upcoming鈥麻豆传媒鈥檚 Ohio Employee Ownership Center (OEOC) will host the 30th Annual Ohio Employee Ownership Conference on Friday, April 29, at the Hilton West in Fairlawn, Ohio. The theme for the conference is 鈥淐elebrating Three Decades of Success: Growing the Employee鈥
麻豆传媒鈥檚 Ohio Employee Ownership Center Hosts 30th Annual Ohio Employee Ownership Conference
麻豆传媒鈥檚 Ohio Employee Ownership Center (OEOC) will host the 30th Annual Ohio Employee Ownership Conference on Friday, April 29, at the Hilton West in Fairlawn, Ohio. The theme for the conference is 鈥淐elebrating Three Decades of Success: Growing the Employee鈥Work in Progress:
Start forming elevator #2 (south).
Grade beam and pile caps along column line #17 between A and G is in progress.
Pile caps for elevator #2 are complete.
Installing pile caps for Stair #3.
Looking forward:
Steel erection sequence #1 will begin on鈥
4/14- ISB Construction Updates
Work in Progress: Start forming elevator #2 (south). Grade beam and pile caps along column line #17 between A and G is in progress. Pile caps for elevator #2 are complete. Installing pile caps for Stair #3. Looking forward: Steel erection sequence #1 will begin on鈥麻豆传媒 will host the annual international conference of the Institute for Complex Adaptive Matter on May 16-18 at the 麻豆传媒 Hotel and Conference Center.
KENT STATE TO HOST ICAM/I2CAM CONFERENCE MAY 16-18
麻豆传媒 will host the annual international conference of the Institute for Complex Adaptive Matter on May 16-18 at the 麻豆传媒 Hotel and Conference Center.Work in Progress:
Pulling wire throughout for branch circuits.
Installing duct on 1st floor.
Complete domestic water rough-in on the 2nd floor.
Sanitary piping rough-in has been completed on the 3rd floor.
Completing remaining framing throughout.
Starting door frame鈥
4/7- Smith Hall Renovation Updates
Work in Progress: Pulling wire throughout for branch circuits. Installing duct on 1st floor. Complete domestic water rough-in on the 2nd floor. Sanitary piping rough-in has been completed on the 3rd floor. Completing remaining framing throughout. Starting door frame鈥Work in Progress:
Forming lift 3 on elevator #1.
Working on retaining wall progressing south to column line A7.
Pile caps and foundations for elevator #2 are complete.
Looking forward:
Pour lift #3 on elevator #1 on 4/8/2016.
Steel delivery and erection begins for鈥
4/7- ISB/Williams Hall Construction Updates
Work in Progress: Forming lift 3 on elevator #1. Working on retaining wall progressing south to column line A7. Pile caps and foundations for elevator #2 are complete. Looking forward: Pour lift #3 on elevator #1 on 4/8/2016. Steel delivery and erection begins for鈥麻豆传媒鈥檚 fourth annual Neuroscience Symposium will cover the latest research findings on 鈥淭he Neuroscience of The Social Brain鈥 on April 7-8 at the 麻豆传媒 Hotel and Conference Center located in downtown Kent, Ohio.